Supplied parts: parts from outside with a monitored delivery date
A supplied part is a task for a part that comes from outside: with delivery date, supplier and the tasks that wait for it. Gantway speaks up before a missing part holds up the workshop.
This feature is included in the Pro and Premium plans. Compare plans
The housing comes from the metalworker, the circuit board from the electronics supplier, and only then can assembly start. For parts like these an order has the supplied part: a task with a delivery date, a supplier and the follow-up tasks that wait for it.
Technically a supplied part is a milestone: it shows as a diamond in the Gantt, has no duration, no people and no time bookings, and does not count towards progress. Unlike a plain milestone, though, it is monitored: if the part fails to arrive, Gantway raises a conflict, and if you like, a reminder comes beforehand.
This article covers adding, planning and monitoring. How to book the arrival and enter a new date is explained in Expected supplied parts: book the arrival and move the date.
Adding a supplied part to an order
Sidebar Orders → open the order → tab "Tasks" → button "Supplied part" (next to "Add task"). By default admins and planners may add one, team leads in orders they are assigned to. The "Add supplied part" dialog asks for:
- "Name" — required, up to 200 characters, e.g. "Housing type A".
- "Delivery date" — optional. Without a date the part shows "Date missing"; Gantway never fills in a substitute date. You can add the date at any time. Gantway rejects a date in the past.
- "Supplier" — free text, with suggestions from the suppliers of your articles.
- "Material item" — optionally the material item of this order the part belongs to. A goods receipt in the inventory then books the part as well, see linking with the material.
- "Follow-up tasks" — the tasks of this order that wait for the part. Without one, the dialog says "Without a follow-up task the part does not affect the plan."
Later you change name and supplier on the expanded part. You add further follow-up tasks on the task in question under "Dependencies", with the supplied part as predecessor (Setting dependencies). Deleting moves the part to the trash; the follow-up tasks then no longer wait for it.
In an order that belongs to a quote not yet accepted, the button is not there. Supplied parts only get into such orders through templates.
What the part does to the plan
- The date is fixed. A supplied part with a date is pinned; neither scheduling nor the cascade moves it. It changes only through "New date" or by booking the arrival.
- Follow-up tasks start on the delivery day at the earliest, from the start of work. If a task waits for several parts, the latest one counts. A buffer is added as usual.
- Delivery day off work: Gantway keeps the date and says so: "… is not a working day. Follow-up tasks start on the next working day at the earliest."
- In the scheduling dialog Gantway names parts without a date ("No delivery date yet: … Scheduling stays possible.") and the part that determines the earliest start of a task, e.g. ""Assembly" starts on 18.11.2026 at the earliest because it waits for "Housing type A"." For follow-up tasks it suggests nothing before the delivery day.
- In the Gantt the part is a diamond, red from the day after a missed date. It cannot be dragged; a click opens "New date" for everyone allowed to change the date.
Notes on the follow-up tasks
As long as the part is not there, every follow-up task shows "Waiting for: Housing type A (date)", on the task card and under My Work, highlighted when late ("overdue since …"). When the task or its timer is started, the note "This task is still waiting for a part" appears. Starting is still possible: Gantway blocks nothing, it only tells you.
On the desk the folder carries the label "Waiting for part" while a task of the order that has not started yet waits for a part, even before a date is missed.
Supplied parts in templates
If the same part comes up in every similar order, put it in the template: for a new entry choose "Supplied part" instead of "Work step" under "Entry type", with a supplier if you like. The part has no date in the template; it is entered in the order.
Entries that wait for the part select it under "Starts after". An entry can also wait for several entries there, for example assembly for housing and circuit board. When the template is applied, the order gets a supplied part with "Date missing", and the dependencies are kept.
If your plan does not include supplied parts, the template entry is called "Milestone without monitoring", and applying it creates a normal milestone.
Monitoring: the "Supplied part overdue" conflict
A supplied part not booked as arrived becomes a "Supplied part overdue" conflict when
- its date is before today, or
- it has no date and one of its follow-up tasks is already scheduled or running.
Only orders with the status Planned, Released and In Progress are monitored. A part with neither a date nor a follow-up task raises no conflict, because nothing depends on it.
The conflict appears at the latest with the daily morning run, even if nobody changes anything in the order that day. There is exactly one per supplied part, and it does not expire on its own. It only closes when the part is booked as arrived, gets a date from today onwards or is deleted, or when the order is cancelled, completed, deleted or set back to draft. Like any other conflict it shows in the count on the menu item, in the conflict list and its filters, on the dashboard and in the Cockpit traffic light; the resolution view offers "Arrived" and "New date".
The urgency follows the scale of the other conflicts and is re-assessed every morning. The yardstick is the start of the next follow-up task that has not begun yet:
- Critical — it starts within 2 working days, or the delivery date promised to the customer is exceeded. If a follow-up task is already running although the part is missing, the conflict is critical too.
- Warning — it starts within 14 working days.
- Info — anything beyond that, and every overdue part without a follow-up task.
For a part without a date the conflict stays at Info until 2 working days before the next follow-up task starts; after that the scale above applies. For orders with the status Planned it is at most a Warning.
Reminder before the date
So that nobody notices on the delivery day that they should have chased the supplier, Gantway sends a reminder in the morning about parts expected soon. It is set for the whole business under Settings → "Tenant Settings", card "Supplied parts reminder"; only the admin sees this page.
- "Remind before the delivery date" switches the reminder on or off.
- "Lead time in working days" sets how early it comes: 1 to 20 working days according to your company calendar, saved with "Save lead time".
The default is on, with 1 working day of lead time. A change applies from the next morning.
Admins, planners and purchasing/warehouse receive one summary notification per person and day, e.g. "3 Zulieferteile werden erwartet" (3 supplied parts expected), with the parts inside the lead time; the link opens the list in the inventory. Gantway reminds once per part and date, and a new date triggers a new reminder. If a part is already inside the lead time when it is added, the reminder comes the next morning. There is no reminder for parts that have arrived, for parts without a date (the conflict covers those) and for orders that are not scheduled yet.
Notifications
| Notification | When | To whom |
|---|---|---|
| "Zulieferteil überfällig" (supplied part overdue) | a part becomes a conflict | admins, planners, purchasing/warehouse |
| "Zulieferteil jetzt kritisch" (supplied part now critical) | the same conflict becomes critical for the first time | admins, planners, purchasing/warehouse |
| "Liefertermin eines Zulieferteils geändert" (delivery date of a supplied part changed) | purchasing/warehouse entered a new date, with old and new date and note | admins and planners |
| "Zulieferteil ist da" (supplied part has arrived) | a part was booked as arrived; if it came before the date, with the note that the follow-up tasks could start earlier | admins, planners and the people on unfinished follow-up tasks, not the person who booked it |
| "Zulieferteil verspätet eingetroffen" (supplied part arrived late) | as above, but after the date ("Termin war …", the date was …) | as above |
| "1 Zulieferteil wird erwartet" (1 supplied part expected) | morning reminder | admins, planners, purchasing/warehouse |
Gantway reports a delay once, and a second time when it becomes critical. If a new date is missed again, that counts as a new delay. The usual conflict notifications ("Kritischer Konflikt: …") and the morning conflict preview do not cover this conflict type; its notifications are the ones in the table.
Everyone can switch the three notification types off separately for app and email under Settings → "Notifications" in the Material group: "Supplied parts reminder", "Supplied part late or rescheduled" and "Supplied part has arrived". The conflict itself is not affected. More in Notifications.
Where supplied parts do not appear
- Not in the quote. A supplied part never appears on the quote PDF or in the customer portal and has no price. In quote editing a part from a template shows "Not part of the offer. Date and arrival under Warehouse → Expected supplied parts."
- Not monitored before scheduling. In drafts and in quotes that are accepted but not scheduled yet, the part shows in the inventory list but raises neither a conflict nor a reminder: until scheduling the follow-up tasks only carry provisional dates.
- When duplicating, the copy contains the part with "Date missing" and not arrived. An old date and an old arrival are not carried over.
- Completing works with an open part too. It then disappears from the list, and its conflict closes.
Limits
- The supplier is free text. There are no purchase order numbers, order documents or supplier master data.
- A supplied part does not model partial quantities. To plan two deliveries, add two parts.
- Booking several parts as arrived at once is not possible; each part is booked on its own.
- The arrival day is always the day of booking; you cannot choose another.
- The reminder lead time exists only for the whole business, not per part.
- An existing milestone cannot be converted into a supplied part.
- Supplied parts do not appear separately in the 3D live view or on the hall monitor; the Cockpit counts their conflicts.