Expected supplied parts: book the arrival and move the date

The list in the inventory shows which supplied parts are overdue, due today or this week. There you book the arrival with one click and enter a new delivery date with a preview.

This feature is included in the Pro and Premium plans. Compare plans

What a supplied part is and how it gets into the order is explained in Supplied parts: parts from outside with a monitored delivery date. This article is about the daily work after that: what comes when, what is overdue, and what happens when the part arrives or is late.

The list in the inventory

Sidebar Inventory → tab "Expected supplied parts". By default every role except employees sees the tab, from the Pro plan. For each part it shows name, supplier, order (with link), date and follow-up tasks, grouped by

Overdue · Date missing · Today · This week · Later.

  • The search field "Search part, supplier or order" and the "All suppliers" filter help when you call a supplier: filter for them, and you have all their open parts in front of you at once.
  • The list shows parts from orders that are not completed, cancelled or deleted. Draft orders carry the "Draft" badge; Gantway does not monitor anything there yet.
  • Parts that have arrived drop out of the default view. With the "Arrived (14 days)" filter you still see them for 14 days and can undo the arrival there.
  • If the list is empty, no supplied part has been added yet: you do that in the order under "Tasks" with the "Supplied part" button.

The "Arrived" and "New date" buttons appear on every part you may work on: by default for admins, planners and purchasing/warehouse, for team leads in orders they are assigned to.

Booking the arrival: "Arrived"

When the part is here, one click on "Arrived" is enough. The button is in three places: in the list, on the part in the order's "Tasks" tab and in the resolution view of the "Supplied part overdue" conflict.

Who may book: by default admins, planners and purchasing/warehouse, team leads in orders they are assigned to. In addition employees assigned to an unfinished follow-up task of the part. They book on the part in the order or under My Work at the "Waiting for: …" note, and can undo it right there in the confirmation. Employees may not change a date.

What the booking does:

  • It does not change the order status. Booking works in every status except Completed and Cancelled, including before release.
  • The part then shows "Arrived on …, booked by …"; the booking is also recorded in the audit log.
  • If the part came early, the diamond moves to the arrival day. The follow-up tasks stay where they are; Gantway pulls nothing forward. The "Zulieferteil ist da" (supplied part has arrived) notification points out that they could start earlier. If you pull one forward by hand, no conflict arises.
  • If it came late, the diamond moves to today. Follow-up tasks that have not started and would otherwise lie before it move back; none starts before the arrival, even if the part only arrives after hours, in which case it starts the next working day. The message after booking names what moved and whether the delivery date promised to the customer is at risk.
  • The arrival day is always the day of booking. If the part came three days ago, book it today anyway and adjust the plan by hand afterwards if needed.

Undo: if the booking was a mistake or the part is defective, undo it with "Undo". The same roles may do this, employees only their own booking. The "Undo the booking?" dialog adds: "Dates that have already moved do not move back automatically." The part gets back its date from before the arrival, "Date missing" included, unless someone deliberately changed it afterwards. For a defective part, then enter a new date with a note.

New delivery date with preview

When the supplier reports a different date, enter it with "New date": in the list, on the part in the order, in the conflict or by clicking the diamond in the Gantt. By default admins, planners and purchasing/warehouse may do this, as well as team leads in orders they are assigned to.

In the "New delivery date" dialog pick the "New date" and add a "Note" if you like, e.g. "Supplier reports week 47". Before you save, "What this date triggers" shows:

  • which tasks move, with old and new start,
  • the "New order end",
  • whether the delivery date promised to the customer is at risk, even if no task moves but the part only comes after that promise.

If something changed between preview and saving, Gantway saves nothing and asks you to check again.

The rules:

  • A later date moves the follow-up tasks that have not started. An earlier date pulls nothing forward.
  • Follow-up tasks that are already running or pinned stay where they are. Gantway says so before you save; afterwards conflict detection reports a violated dependency.
  • Gantway rejects a date in the past, and the date the part is already on.
  • A part that has arrived can only get a new date after the arrival is undone.
  • Every change is listed in the "Date history" on the expanded part: who changed which date to which and when, with the note. If purchasing/warehouse changed the date, admins and planners receive the notification "Liefertermin eines Zulieferteils geändert" (delivery date of a supplied part changed).

Linking with the material

If the part belongs to a material item of the order, link the two on the expanded part in the "Material item" field (or right when adding it). A material item belongs to at most one supplied part; Gantway suggests name and supplier from the article. Admins, planners, team leads in orders they are assigned to and purchasing/warehouse may link.

  • Goods receipt books along: when the material item changes to "Delivered", the part counts as arrived, with all the effects described above. That happens by hand with "Mark as delivered" in the to-buy list or automatically when a goods receipt covers the item's demand. The part then shows "The booking came from the warehouse."
  • Only from "Ordered": only an item on "Ordered" switches automatically. If it is still on "To order" or "From stock", the part says: "A goods receipt only books the part once the material item is "Ordered". Until then, book the arrival on the part itself." Whoever may edit the material item finds the "Set to "Ordered"" button next to it.
  • The other way round: "Arrived" on the part sets an ordered material item to "Delivered". It does not change stock; Gantway reminds you that the goods receipt still has to be booked in the inventory. An item on "To order" or "From stock" stays as it is.
  • Undo sets the material item back to where it was before the arrival, if the arrival had changed it; it does not reverse a stock booking. If someone takes "Delivered" back on the material item, the part is open again too.
  • Already delivered: if you link to an item that is already "Delivered", Gantway asks "Link to a delivered material item?". Confirming books the part as arrived, and the planners are notified. A part that has arrived can only be relinked after the arrival is undone.
  • Material gone: if the material item is deleted, rejected or marked "Not needed", the part stays open and shows a note in the list.

If the stock only covers some of the orders that need the same article, only the covered items count as delivered. The other parts stay open and remain monitored.

Also known as: supplied part arrived, part is here, delivery late, move delivery date, supplier reports new date, undo arrival, chase supplier.