Assigning employees

On the task or by dragging from the team dock — two ways to put someone on a task. From 90% weekly utilization, Gantway asks first.

Who does the work? There are two routes for assigning it. By default both are open to admin, planner and team lead.

Route 1: on the work step

  1. Open Orders in the sidebar and click the order.
  2. Go to the "Tasks" tab and expand the work step.
  3. Pick the person in the "Assignments" section. Gantway confirms: "Employee assigned to task."

The classic route when you are working in the order anyway.

Route 2: dragging from the team dock

  1. Open Desk in the sidebar and switch to "Project Overview". The team dock sits below the Gantt and shows your team along with their utilization.
  2. Drag an avatar directly onto a bar. On touch devices a long press (about half a second) on the avatar replaces the drag; a selection sheet opens.
  3. Gantway confirms with "{name} zugewiesen" (assigned).

The advantage: you see while assigning who still has capacity, instead of finding out afterwards. How to read the utilization display is covered in Team dock: reading utilization.

After the assignment the dialog "Termine neu berechnen?" (recalculate dates?) may follow, if the change touches dependent dates. See how the cascade pulls dates along.

Auch bekannt als: assign, assignment, schedule staff, who does what, overload.