How the cascade pulls dates along
When one step shifts, Gantway pulls all dependent dates along — under two conditions. Why follow-up dates sometimes do not move.
The cascade is the core of Gantway: when one work step shifts, Gantway recalculates the dates of all dependent steps — including free gaps in the resources and taking into account what other orders already occupy there.
Two conditions for the cascade to take effect
- There is at least one dependency. Without a chain, every task is scheduled individually — nothing "knows" that it should move up. That is the most common answer to "Why aren't my follow-up dates shifting?": set dependencies.
- The task is not a fixed point. Three kinds of task are never moved by the cascade: pinned ones (see below), running ones and finished ones. What has started or been completed is not re-dated retroactively.
Planning always runs forward, from the start. The cascade never moves the date you promised the customer; it sits on the order as the delivery date, and Gantway warns when the planned end slips past it.
Recognising and releasing pinned tasks
A task gets pinned when you drag its bar in the Gantt (only that one bar; successors moved along stay free) or resolve a conflict with "Reschedule". Some of these labels are not translated; German labels are quoted with the meaning in brackets. You recognise the pin in three places:
- in the Gantt by a small pin tag on the bar, with the tooltip "Fixiert – die automatische Terminierung verschiebt diese Position nicht." (pinned — automatic scheduling does not move this position),
- in the item card in the "Tasks" tab by the badge "Fixiert" (pinned),
- in the expanded work step by the row "Termin fixiert" (date pinned) with a switch.
You release or set the pin by clicking the bar in the Gantt (menu item "Fixierung lösen" — release pin — or "Fixieren" — pin), by clicking the "Fixiert" badge or via the switch. Releasing does not move anything yet: "Fixierung gelöst – beim nächsten Umplanen kann die Position verschoben werden." (pin released — the position can be moved at the next rescheduling). In the order Gantt and on the item card, admins, planners and team leads may do this by default; in the desk Gantt, admins and planners.
You have the final word
For changes to the date, duration or buffer on a work step and to the order's start date, Gantway asks "Recalculate dates?" beforehand and lists every affected position with its old and new time range: "Your change shifts the dates of {n} position(s). … Already running or completed positions remain unchanged." With "Apply dates" the shift runs; with "Don't move" everything stays put. More under Recalculating deadlines.
Buffer between the steps
After each predecessor, the cascade adds its "buffer minutes" to the following date — the slack for drying, retooling, transport. The "Buffer" field sits on the expanded work step in the order's "Tasks" tab; if it is empty, the order's default value applies.